SPEED-ENDEAVOR

LEARNING-SOMETHING-INTERESTING

Thursday, June 25, 2009

Analog transmitter calibration

  1. Prior to commencement, refer to manufacturers recommended calibration procedure for this device. This is general terms for a pressure transmitter and in certain circumatances it may be the case that a characteristic of the instrument under test differs from this procedure.
  2. Check instrument against data sheet, P&ID and layout drawings.
  3. Record transmitter range. Output indication shall be calibrated with the transmitter. Record the instrument supply in.
  4. Simulate process variable that the device shall measure ie hydraulic or pneumatic pressure calibrator, temperature bath, manually move equipment, test solution for SG, ph or conductivity. Float type solution interface transmitters must be tested with suitable test fluid (simillar composition and SG). Suitable method of transport and handling the fluids must be provided. Determining the level in measurement chamber must be developed and agreed with the responsible engineer. Transmitter on oxygen service must be subject to pneumatic test only.
  5. Connect the output of transmitter to either the suitable test meter (electrical) or test gauge (pneumatic).
  6. By varying the simulated input signal incerasing and decreasing accordingly set zero and full scale to within the manufacturers tolerance.
  7. Apply varying simulated input 0%, 25%, 50%, 75%, and 100% and decreasing back to 0%
  8. Calculate percetage error if applicable
  9. Reinstate the device and check installation detail, sign and date accordingly.
  10. Attached any "As Built" drawings or sketches. must be stamped "As Built" and signed/date both in red ink.
  11. Record any defect and deviation on data sheet and sign off ITRs as complete by printing and signing name and date in "Inspected by section"

Tuesday, June 23, 2009

Power & Control Cable Pre-commissioning

Cek dan Pastikan

  1. Compare cable size, type and tagging with the cable schedule. Ensure core identification match with connection diagram and phase sequence
  2. Check the glands certificate meet the area classification as mentioned in spec
  3. Inspect the glands cable for tighness and good workmanship; correct type and size of cable installed. Check the outdoor glands have been wrappen in vulcanising tape
  4. Ensure the gland plates for all single cables have been manufactured from non magnetic materials
  5. Pastikan conductors are terminated using crimped connections. check correct size and type of crimping lugs has been used
  6. Before making any measurement, inspector should ensure both ends of the cable has been disconnected and are clear of any metal
  7. Cek the earth connection


Insulation Resistance Test

Ukur insulation resistance of the cable on record on the relevant certifiacte. Table di bawah memberikan minimum test voltage and minimum acceptable value of insulation resistance.

For LV multicore measurement shall be
  1. core to core

  2. core to earth

  3. screen to armour









Switchgear Pre-commissioning

Switchgear pre-installation inspection
  1. Pastikan equipment certificate meet area classification requirement

  2. Remove temporary weather proofing, transport packing, and silica gel drying agent from switchgear, Cek cleanliness di dalam switchgear, specially for insulator

  3. Compare switchgear equipment meets equipment schedule, specially rating and any circuit changes

  4. Pastikan equipment meets spec, including weather, dust and vermin proofing

Switchgear post-installation inspection

  1. Check switchboard assy for alignment, level, tighteness foundation bolts and fixing in general

  2. Pastikan all panel doors and gland plate are bonded to switchboard structure

  3. Pastikan all equipment installed in switch board are in good conditions

  4. Inspect busbar joint

  5. Pastikan all insulators are clean, free from damage and not subjected to undue mechanical stress

  6. Cek all items corresponded to material list

  7. Cek all damages items

  8. Clearence phase to phase and phase to earth are acordance with spec

  9. Section clearances are satisfactory

  10. Earthing connection connected to all necessary points and clear of other metal

  11. Earthing connection tight, greased and thinned as required. Inspect the switchboard earth bar and earth cable for electrical and mechanical continuity

  12. Confirm all earth runs connected to main grid

  13. Labels correct/fitted

  14. Manufacturers name plate/marker correct/fitted

  15. Serial numbers match manufacturers test certificates

  16. Primary connection assembly /jointing compound, no undue stress/tension on equipment, fitting bolt correctly tensioned

  17. No dissimilar metals employed on primary connections

  18. No rust on equipment

  19. Site surfacing is correct and satisfactory

  20. All fixing bolts are tight

  21. No leaking impregnation fluid or swelling of containers

  22. Ensure all manufacturer's document and test certificate have been received

  23. Operation of locking facilities

  24. Cable entry arrangments

  25. Ensure all equipments meet specification weather, dust and vermin proofing after installation

  26. Examine fuses for rupturing or signs of deterioration

Switchborad testing

  1. After all busbar joints are completed but prior to securely fitting busbar covers, measure insulation resistance of the busbars and control wiring.

  2. Where there are any busbar joints, ductor test must be carried out prior to fitting covers. Simillar joints shall have a contact resistance within 10% of each other. The joints shall have a resistance equal or lower than an equivalent section of busbar

  3. Test switch board earth system for electrical dan mechanical continuity. Measure earth path resistance at the earth bar to the general earth system and earth bar joints

  4. Ensure that all protection relay have been tested accrdance with requirement of appropriate test certificate and vendor instruction

  5. Measure insulation testing of busbar and control wiring. Test should be carrued out prior to pressure test and before energising switchboard. Minimum acceptabe test result as below. A Power frequency voltage test (pressure test) on both main and outgoing cicuits sall be carried out phases and phases to earth.


                Following conection shall be adhered for the tests

                1. All secondary sides of current transformers shall be short circuit
                2. All secodary sides of voltage transformer shall be open circuit

                upon completion all tests, reconnect all cables and ensure that shorting links and fuses are replace





                Monday, June 22, 2009

                Electrical & Instrument Fabrication Drawing

                What kind of electrical and instrument drawing can be found in fabrication of an oil and gas fabrication project. This only an overview and few drawing samples for who wants to know about a project fabrication -construction, specially for electrical and instrument disciples area. Actually quantity and kinds of drawing are depend on system which are already designed and approved by Engineering and client or project owner.

                Dalam suatu project construction biasa kita temukan istilah EPCI. Biasa setelah bidding project selesai, maka akan di announce pemenang project. Missal untuk engineering dan procurement di menangkan oleh PT A, untuk fabrikasi dimenangkan oleh PT B, untuk offshore installation dimenangkan oleh PT C. Tapi ada juga untuk EPCI ini dimenangkan oleh satu perusahaan.

                E stands for Engineering,
                Engineering is body/company who have designed a project. Here will be discussed and decided about a system made, material consumed, manpower required included skill and competency, method agreed, machine used and how to manage activities and communication flow among discipline, management, contractor, client, owner, third parties inspection and classification

                P is Procurement,
                Normally procurement is how to procure after dealing with supplier and vendor material and schedule delivery and receiving and where are put ; warehouse or need certain condition reservation

                C is Construction,
                Construction is done in site, usually in a yard. Normally yard is located in seashore in order easy to bring product CPP or modules to offshore installation location. First maybe preparation of civil and foundation activities, than structural installation, piping installation, electrical installation and instrument installation, and lastly pre commissioning.

                I is Installation,
                After fabrication finished, next stage is installation. the product will be pulled to edge of sea and put on the barge and do sea fastening and ready to sail away to installation place. During this time shall be prepared all items for offshore installation, lifting equipment capacity, competent crews, scenario of installation etc

                Sekarang kita jump to topic about Electrical & instrument drawing. Actually each client or owner or company have their specification. They have their own terminology like few companies use term “grounding” ,others use term “earthing”. All terminologies actually are agreement in specification /datasheet/manufacturing sheet. All depend how they define and name in their document

                ELECTRICAL DESIGN DRAWING
                Electrical/PAGA/Navigational Aid index, legend, symbol & notes
                Electrical/PAGA/Navigational Aid single line diagram or one line diagram
                lectrical/PAGA/Navigational Aid block diagram
                Electrical/PAGA/Navigational Aid schematic/logic/loop/wiring/interconnection diagram
                Electrical/PAGA/Navigational Aid layout
                Electrical/PAGA/Navigational Aid installation Details
                Electrical/PAGA/Navigational Aid cable/panel Schedule
                Electrical main tray/ladder support detail
                Hazardous area classification
                Electrical design miscellaneous

                ELECTRICAL SHOP AND INSTALLATION (Field Run) DRAWING
                Electrical power routing layout
                Electrical Power tray support layout
                Electrical Power tray support detail
                Electrical Power mounting support layout
                Electrical Power mounting support detail
                Electrical Equipment support layout
                Electrical Equipment support detail
                Lighting cable routing
                Lighting tray support layout
                Lighting tray support detail
                Lighting mounting support layout
                Lighting mounting support detail
                Navigation aid mounting support layout
                Navigation aid mounting support Detail
                PAGA cable tray support layout
                PAGA cable tray support detail
                PAGA mounting support layout
                PAGA mouting support detail
                Electrical/PAGA cable penetration layout
                Electrical/PAGA cable penetration detail
                Electrical Shop Miscellaneous

                INSTRUMENT DESIGN DRAWING
                Instrument/ Fire & Gas/Telecommunication index, legend, symbol & notes
                Instrument process cause & effect diagram
                Instrument safety cause & effect diagram
                Instrument shutdown hierarchy diagram
                Instrument blok diagram
                Instrument interconnection/loop /termination/wiring/interface/schematic/logic diagram
                Instrument layout
                Instrument installation/support/mounting detail
                Instrument hook up
                Instrument cable/tubing/panel schedule
                Instrument level sketches
                Instrument main tray/ladder support detail
                Instrument miscellaneous

                Fire and Gas cause & effect diagram
                Fire and Gas single line/interconnection/loop diagram /termination/
                Fire and Gas wiring/interface/schematic/logic diagram
                Fire and Gas block diagram
                Fire and Gas layout
                Fire and Gas installation/mounting detail
                Fire and Gas miscellaneous
                Safety Escape route/sign layout

                Telecom single line diagram
                Telecom /interconnection/loop diagram /termination/wiring/logic diagram
                Telecom cable routing layout
                Telecom block diagram
                Telecom layout
                Telecom installation/mounting detail
                Telecom miscellaneous

                INSTRUMENT SHOP/INSTALLATION DRAWING
                Instrument mounting support layout
                Instrument installation detail
                Instrument tubing routing
                Instrument tubing tray support Layout
                Instrument tubing tray support detail
                Instrument cable tray support Layout
                Instrument cable tray support detail
                Fusible plug mounting layout
                Fusible plug detail
                Fusible plug tray support Layout
                Fusible plug tray support detail
                Fire & Gas mounting support layout
                Fire & Gas mounting support detail
                Fire & Gas cable tray support layout
                Fire & Gas cable tray support detail
                Telecom mounting support layout
                Telecom mounting support detail
                Telecom cable tray support layout
                Telecom cable tray support detail
                Instrument Tubing/cable Penetration layout
                Instrument Tubing/cable Penetration Detail
                Instrument Junction Box Support layout
                Instrument Junction Box Support Detail


                Few drawing samples for Electrical Discipline :
                1. Legend. Legend tells all symbols which are used in drawing in order whoever read drawing can understand everything on drawing
                There are several national and international standards for graphical symbols in circuit diagrams, in particular:
                · IEC 60617 (also known as British Standard BS 3939)
                · ANSI standard Y32 (also known as IEEE Std 315)












                2. Single line diagram. Ada juga memakai istilah one line diagram. Ini biasa nya men deskripsi kan tentang aliran daya listrik, start from generator, bus duct, switchgear, transformer, ke distribution board, than supply untuk
                - motor /pump/ fan/ compressor
                - space heater
                - lighting
                - fire and gas panel
                - Public address and general alarm panel
                - Telecommunication panel
                - Instrument supply panel etc








                3. Block diagram. Di dalam block diagram biasa nya menggambarkan interrelationship among system and existing equipment in global view, usually for electrical about cabling relationship. Below are lighting block diagram sample








                4. Wiring diagram/Interconnection diagram/loop diagram/schematic diagram. so far I have found They are almost same. All are about wiring or cabling detail for real connection. All connection should be labeled by tag no or cable marker for tracking and identification. Below are samples of Junction box







                and turbine-generator wiring connection.








                5. Plan or layout drawing. Plan show location of equipment. Plan usually base on system. E.g. lighting plan, fire and gas plan, public address and general alarm plan, telecommunication plan, navigational aid plan. Below is sample of fire and gas plan








                6. Detail installation drawing. These are detail installation for each equipments or detector or sensor which are given in plan drawing included with each bill of material for each installation. So each plan drawing will have all kinds of detail installation for all equipments /detectors /sensor which are put in plan drawing. Below is sample of strobe light installation detail










                Few drawing samples Untuk Instrument Discipline


                1. Instrument hook up. Hook up is similar with installation detail. See below picture










                2. Instrument Tray support detail. This tells about support of main tray or ladder












                3. Instrument layout. This give information about location of instrument in the field











                5. Instrument Fusible plug plan & detail

                Wednesday, June 3, 2009

                IEC Index

                IEC 60038 Standard voltages
                IEC 60076-2 Power transformers - Temperature rise
                IEC 60076-3 Power transformers - Insulation levels, dielectric tests and external clearances in air
                IEC 60076-5 Power transformers - Ability to withstand short-circuit
                IEC 60076-10 Power transformers - Determination of sound levels
                IEC 60146 Semiconductor convertors - General requirements and line commutated convertors
                IEC 60255 Electrical relays
                IEC 60265-1 High-voltage switches - High-voltage switches for rated voltages above 1 kV and less than 52 kV
                IEC 60269-1 Low-voltage fuses - General requirements
                IEC 60269-2 Low-voltage fuses - Supplementary requirements for fuses for use by unskilled persons (fuses mainly for household and similar applications)
                IEC 60282-1 High-voltage fuses - Current-limiting fuses
                IEC 60287-1-1 Electric cables - Calculation of the current rating - Current rating equations (100% load factor) and calculation of losses - General
                IEC 60364 Electrical installations of buildings
                IEC 60364-1 Electrical installations of buildings - Fundamental principles
                IEC 60364-4-41 Electrical installations of buildings - Protection for safety - Protection against electric shock
                IEC 60364-4-42 Electrical installations of buildings - Protection for safety - Protection against thermal effects
                IEC 60364-4-43 Electrical installations of buildings - Protection for safety - Protection against overcurrent
                IEC 60364-4-44 Electrical installations of buildings - Protection for safety - Protection against electromagnetic and voltage disrurbance
                IEC 60364-5-51 Electrical installations of buildings - Selection and erection of electrical equipment - Common rules
                IEC 60364-5-52 Electrical installations of buildings - Selection and erection of electrical equipment - Wiring systems
                IEC 60364-5-53 Electrical installations of buildings - Selection and erection of electrical equipment - Isolation, switching and control
                IEC 60364-5-54 Electrical installations of buildings - Selection and erection of electrical equipment - Earthing arrangements
                IEC 60364-5-55 Electrical installations of buildings - Selection and erection of electrical equipment - Other equipments
                IEC 60364-6-61 Electrical installations of buildings - Verification and testing - Initial verification
                IEC 60364-7-701 Electrical installations of buildings - Requirements for special installations or locations - Locations containing a bath tub or shower basin
                IEC 60364-7-702 Electrical installations of buildings - Requirements for special installations or locations - Swimming pools and other basins
                IEC 60364-7-703 Electrical installations of buildings - Requirements for special installations or locations - Locations containing sauna heaters
                IEC 60364-7-704 Electrical installations of buildings - Requirements for special installations or locations - Construction and demolition site installations
                IEC 60364-7-705 Electrical installations of buildings - Requirements for special installations or locations - Electrical installations of agricultural and horticultural
                premises
                IEC 60364-7-706 Electrical installations of buildings - Requirements for special installations or locations - Restrictive conducting locations
                IEC 60364-7-707 Electrical installations of buildings - Requirements for special installations or locations - Earthing requirements for the installation of data
                processing equipment
                IEC 60364-7-708 Electrical installations of buildings - Requirements for special installations or locations - Electrical installations in caravan parks and caravans
                IEC 60364-7-709 Electrical installations of buildings - Requirements for special installations or locations - Marinas and pleasure craft
                IEC 60364-7-710 Electrical installations of buildings - Requirements for special installations or locations - Medical locations
                IEC 60364-7-711 Electrical installations of buildings - Requirements for special installations or locations - Exhibitions, shows and stands
                IEC 60364-7-712 Electrical installations of buildings - Requirements for special installations or locations - Solar photovoltaic (PV) power supply systems
                IEC 60364-7-713 Electrical installations of buildings - Requirements for special installations or locations - Furniture
                IEC 60364-7-714 Electrical installations of buildings - Requirements for special installations or locations - External lighting installations
                IEC 60364-7-715 Electrical installations of buildings - Requirements for special installations or locations - Extra-low-voltage lighting installations
                IEC 60364-7-717 Electrical installations of buildings - Requirements for special installations or locations - Mobile or transportable units
                IEC 60364-7-740 Electrical installations of buildings - Requirements for special installations or locations - Temporary electrical installations for structures,
                amusement devices and booths at fairgrounds, amusement parks and circuses
                IEC 60427 High-voltage alternating current circuit-breakers
                IEC 60439-1 Low-voltage switchgear and controlgear assemblies - Type-tested and partially type-tested assemblies
                IEC 60439-2 Low-voltage switchgear and controlgear assemblies - Particular requirements for busbar trunking systems (busways)
                IEC 60439-3 Low-voltage switchgear and controlgear assemblies - Particular requirements for low-voltage switchgear and controlgear assemblies intended to
                be installed in places where unskilled persons have access for their use - Distribution boards
                IEC 60439-4 Low-voltage switchgear and controlgear assemblies - Particular requirements for assemblies for construction sites (ACS)
                IEC 60446 Basic and safety principles for man-machine interface, marking and identification - Identification of conductors by colours or numerals
                IEC 60439-5 Low-voltage switchgear and controlgear assemblies - Particular requirements for assemblies intended to be installed outdoors in public places
                - Cable distribution cabinets (CDCs)
                IEC 60479-1 Effects of current on human beings and livestock - General aspects
                IEC 60479-2 Effects of current on human beings and livestock - Special aspects
                IEC 60479-3 Effects of current on human beings and livestock - Effects of currents passing through the body of livestock
                (Continued on next page)
                2 Rules and statutory regulations
                Schneider Electric - Electrical installation guide 2007
                A - General rules of electrical installation design
                A
                IEC 60529 Degrees of protection provided by enclosures (IP code)
                IEC 60644 Spécification for high-voltage fuse-links for motor circuit applications
                IEC 60664 Insulation coordination for equipment within low-voltage systems
                IEC 60715 Dimensions of low-voltage switchgear and controlgear. Standardized mounting on rails for mechanical support of electrical devices in switchgear
                and controlgear installations.
                IEC 60724 Short-circuit temperature limits of electric cables with rated voltages of 1 kV (Um = 1.2 kV) and 3 kV (Um = 3.6 kV)
                IEC 60755 General requirements for residual current operated protective devices
                IEC 60787 Application guide for the selection of fuse-links of high-voltage fuses for transformer circuit application
                IEC 60831 Shunt power capacitors of the self-healing type for AC systems having a rated voltage up to and including 1000 V - General - Performance, testing
                and rating - Safety requirements - Guide for installation and operation
                IEC 60947-1 Low-voltage switchgear and controlgear - General rules
                IEC 60947-2 Low-voltage switchgear and controlgear - Circuit-breakers
                IEC 60947-3 Low-voltage switchgear and controlgear - Switches, disconnectors, switch-disconnectors and fuse-combination units
                IEC 60947-4-1 Low-voltage switchgear and controlgear - Contactors and motor-starters - Electromechanical contactors and motor-starters
                IEC 60947-6-1 Low-voltage switchgear and controlgear - Multiple function equipment - Automatic transfer switching equipment
                IEC 61000 Electromagnetic compatibility (EMC)
                IEC 61140 Protection against electric shocks - common aspects for installation and equipment
                IEC 61557-1 Electrical safety in low-voltage distribution systems up to 1000 V AC and 1500 V DC - Equipment for testing, measuring or monitoring of protective
                measures - General requirements
                IEC 61557-8 Electrical safety in low-voltage distribution systems up to 1000 V AC and 1500 V DC - Equipment for testing, measuring or monitoring of protective
                measures
                IEC 61557-9 Electrical safety in low-voltage distribution systems up to 1000 V AC and 1500 V DC - Equipment for insulation fault location in IT systems
                IEC 61558-2-6 Safety of power transformers, power supply units and similar - Particular requirements for safety isolating transformers for general use
                IEC 62271-1 Common specifications for high-voltage switchgear and controlgear standards
                IEC 62271-100 High-voltage switchgear and controlgear - High-voltage alternating-current circuit-breakers
                IEC 62271-102 High-voltage switchgear and controlgear - Alternating current disconnectors and earthing switches
                IEC 62271-105 High-voltage switchgear and controlgear - Alternating current switch-fuse combinations
                IEC 62271-200 High-voltage switchgear and controlgear - Alternating current metal-enclosed switchgear and controlgear for rated voltages above 1 kV and up to
                and including 52 kV
                IEC 62271-202 High-voltage/low voltage prefabricated substations
                (Concluded)

                Monday, March 16, 2009

                Electrical Hook up general note for instrument installation












                1. Instrument hook up and installation for instrument wiring system shall be accordance with specifications (Instrument design basis & instrument installation specification)
                2. The hook up and installation drawings shown in general the required position of the instrument relative to measuring point. The exact location shall be determined at the site with the aid of instrument location drawings
                3. All instruments shall be installed in such a way that they are not subjected to
                  - Unable to access
                  - excessive vibration
                  - extreme environment conditions
                  - obstruct traffic
                  - periodic maintenance of adjacent equipmentbe installed in place which are prone to leakage/dripping
                4. Sufficient space shall be left around the instrument for instrument cover removal /withdrawal and for removal protective shades. The minimum clearance between any parts and instrument and surrounding structures or equipment shall not be less than 0.2m to allow insulation, painting, etc
                5. Sufficient flexibility shall be provided in instrument cable line to allow thermal expansion the line equipment to which they connect
                6. All fabricated work in the field shall be grounded smooth and painted as per project standards. All painting shall be carried out before attachment of instruments, cables, tubing, etc. to the painted materials
                7. All instrument cables and wiring shall be identified with the drawings and as detailed in instrument basis. Instrument cable shall be tagged with 316SS tags at walls, penetration and at the end points
                8. Wiring to terminal blocks shall not exceed two connections per terminal point
                9. A short coil of cable shall be made in field cable at instrument
                10. Every wire in every cable including spare wires and drain wires shall be terminated with a company approved insulated ferule, on rail mounted terminal blocks , at both end
                11. Each terminal point (including end devices, junction boxes and marshalling strips) shall be made up to include heat shrink insulation over cable and wire shields, end and bare drain wires
                12. All cable shields shall be earthed at IER (Instrument Equipment Room) and CCR (Control Center Room) only. Individual shields drain wires for pairs and triad shall be cut, coil and taped at the instrument head
                13. All multi core pair and triad overall shields and drain wires shall be insulated green/yellow colored PVC sleeving
                14. All metallic components, others than current carrying conductors shall be connected to a common earth system. All unused cable cores shall be earthed at one end only
                15. cable runs that penetrate walls (E.G. building walls, blast walls and fire walls) that separate safe area hazardous (classified) shall be provided with vapor tight cable transits fire rated to meet the fire wall requirements

                Wednesday, March 11, 2009

                Generator Electrical Protective Relay Devices base on ANSI


                Over excitation protection Volt/Hertz relay (ANSI No.24)

                Relay ini harus di-set untuk meng-counter high induction
                proporsional dengan V/f, yang mengakibatkan thermal
                overloading. These may occur during starting and shut


                Picture :
                ABB-product series-compact and integrated with multi protectiondown under full load condition




                Under voltage relay (ANSI No.27)
                This relay prevents generator/motor to operate below normal voltage/frequency operating system cause by AVR or internal faults. Time delay must be set slower than transient system voltage dip and must be faster than too much slowing down generator and make re accelerate to meet proper plant recovery

                Reverse power relay (ANSI No. 32)
                This device protects generator to receive power from system in case of failing prime mover to drive generator. Turn back power may damage generator.

                Lost of excitation relay (ANSI No. 40)
                Faulty in generator field excitation circuitry causes generator loss of excitation. In this case generator will act as induction generator which received reactive power from system. This condition will make instability in power system and over heating on damper rotor windings

                Negative sequence relay (ANSI No.46)
                These are included to detect phase unbalance, phase reversal, and phase sequence fault. These abnormal condition will heat machine windings. This kind of relay is more independent to do close/open power system

                Inadvertent energizing relay (ANSI No. 50/27)
                Due to unintentionally energizing will make generator damage. This relay will limit down possibility of generator damage. Actually this relay is combination of over current relay and under voltage relay with controlling electronic digital logic.

                Breaker failure relay (ANSI No.50BF)
                In the event of a downtimes or faulty in generator, generator can remain online if the breaker is defective or substantial damage. This protection will measure minimum breaker current and thru auxiliary contact. It can be activated via internal protective tripping or externally via binary input

                Sensitive earth fault relay (ANSI No.50/51G)
                This device is for Limiting damage of generator in the event of rotor earth fault. The sensitive earth fault can be use as separate earth fault protection

                Definite time over current relay (ANSI No.50/51)
                This is short circuit protective device

                Inverse time over current relay (ANSI No 51V)
                This is also short circuit protective device with ANSI and IEC curve characteristic respond. This can be selected base on system requirement

                Over voltage relay (ANSI No.81U)
                This protect generator voltage regulator that could be damaged in an over voltage condition due to AVR failure or manual voltage control errors. A time delay is provided to prevent tripping under transient voltage spikes