Thursday, June 25, 2009

Analog transmitter calibration

  1. Prior to commencement, refer to manufacturers recommended calibration procedure for this device. This is general terms for a pressure transmitter and in certain circumatances it may be the case that a characteristic of the instrument under test differs from this procedure.
  2. Check instrument against data sheet, P&ID and layout drawings.
  3. Record transmitter range. Output indication shall be calibrated with the transmitter. Record the instrument supply in.
  4. Simulate process variable that the device shall measure ie hydraulic or pneumatic pressure calibrator, temperature bath, manually move equipment, test solution for SG, ph or conductivity. Float type solution interface transmitters must be tested with suitable test fluid (simillar composition and SG). Suitable method of transport and handling the fluids must be provided. Determining the level in measurement chamber must be developed and agreed with the responsible engineer. Transmitter on oxygen service must be subject to pneumatic test only.
  5. Connect the output of transmitter to either the suitable test meter (electrical) or test gauge (pneumatic).
  6. By varying the simulated input signal incerasing and decreasing accordingly set zero and full scale to within the manufacturers tolerance.
  7. Apply varying simulated input 0%, 25%, 50%, 75%, and 100% and decreasing back to 0%
  8. Calculate percetage error if applicable
  9. Reinstate the device and check installation detail, sign and date accordingly.
  10. Attached any "As Built" drawings or sketches. must be stamped "As Built" and signed/date both in red ink.
  11. Record any defect and deviation on data sheet and sign off ITRs as complete by printing and signing name and date in "Inspected by section"

Tuesday, June 23, 2009

Power & Control Cable Pre-commissioning

Cek dan Pastikan

  1. Compare cable size, type and tagging with the cable schedule. Ensure core identification match with connection diagram and phase sequence
  2. Check the glands certificate meet the area classification as mentioned in spec
  3. Inspect the glands cable for tighness and good workmanship; correct type and size of cable installed. Check the outdoor glands have been wrappen in vulcanising tape
  4. Ensure the gland plates for all single cables have been manufactured from non magnetic materials
  5. Pastikan conductors are terminated using crimped connections. check correct size and type of crimping lugs has been used
  6. Before making any measurement, inspector should ensure both ends of the cable has been disconnected and are clear of any metal
  7. Cek the earth connection


Insulation Resistance Test

Ukur insulation resistance of the cable on record on the relevant certifiacte. Table di bawah memberikan minimum test voltage and minimum acceptable value of insulation resistance.

For LV multicore measurement shall be
  1. core to core

  2. core to earth

  3. screen to armour









Switchgear Pre-commissioning

Switchgear pre-installation inspection
  1. Pastikan equipment certificate meet area classification requirement

  2. Remove temporary weather proofing, transport packing, and silica gel drying agent from switchgear, Cek cleanliness di dalam switchgear, specially for insulator

  3. Compare switchgear equipment meets equipment schedule, specially rating and any circuit changes

  4. Pastikan equipment meets spec, including weather, dust and vermin proofing

Switchgear post-installation inspection

  1. Check switchboard assy for alignment, level, tighteness foundation bolts and fixing in general

  2. Pastikan all panel doors and gland plate are bonded to switchboard structure

  3. Pastikan all equipment installed in switch board are in good conditions

  4. Inspect busbar joint

  5. Pastikan all insulators are clean, free from damage and not subjected to undue mechanical stress

  6. Cek all items corresponded to material list

  7. Cek all damages items

  8. Clearence phase to phase and phase to earth are acordance with spec

  9. Section clearances are satisfactory

  10. Earthing connection connected to all necessary points and clear of other metal

  11. Earthing connection tight, greased and thinned as required. Inspect the switchboard earth bar and earth cable for electrical and mechanical continuity

  12. Confirm all earth runs connected to main grid

  13. Labels correct/fitted

  14. Manufacturers name plate/marker correct/fitted

  15. Serial numbers match manufacturers test certificates

  16. Primary connection assembly /jointing compound, no undue stress/tension on equipment, fitting bolt correctly tensioned

  17. No dissimilar metals employed on primary connections

  18. No rust on equipment

  19. Site surfacing is correct and satisfactory

  20. All fixing bolts are tight

  21. No leaking impregnation fluid or swelling of containers

  22. Ensure all manufacturer's document and test certificate have been received

  23. Operation of locking facilities

  24. Cable entry arrangments

  25. Ensure all equipments meet specification weather, dust and vermin proofing after installation

  26. Examine fuses for rupturing or signs of deterioration

Switchborad testing

  1. After all busbar joints are completed but prior to securely fitting busbar covers, measure insulation resistance of the busbars and control wiring.

  2. Where there are any busbar joints, ductor test must be carried out prior to fitting covers. Simillar joints shall have a contact resistance within 10% of each other. The joints shall have a resistance equal or lower than an equivalent section of busbar

  3. Test switch board earth system for electrical dan mechanical continuity. Measure earth path resistance at the earth bar to the general earth system and earth bar joints

  4. Ensure that all protection relay have been tested accrdance with requirement of appropriate test certificate and vendor instruction

  5. Measure insulation testing of busbar and control wiring. Test should be carrued out prior to pressure test and before energising switchboard. Minimum acceptabe test result as below. A Power frequency voltage test (pressure test) on both main and outgoing cicuits sall be carried out phases and phases to earth.


                Following conection shall be adhered for the tests

                1. All secondary sides of current transformers shall be short circuit
                2. All secodary sides of voltage transformer shall be open circuit

                upon completion all tests, reconnect all cables and ensure that shorting links and fuses are replace





                Monday, June 22, 2009

                Electrical & Instrument Fabrication & shop Drawing

                What kind of electrical and instrument drawing can be found in fabrication of an oil and gas fabrication project. This only an overview and few drawing samples for who wants to know about a project fabrication -construction, specially for electrical and instrument disciples area. Actually quantity and kinds of drawing are depend on system which are already designed and approved by Engineering and client or project owner.

                Dalam suatu project construction biasa kita temukan istilah EPCI. Biasa setelah bidding project selesai, maka akan di announce pemenang project. Missal untuk engineering dan procurement di menangkan oleh PT A, untuk fabrikasi dimenangkan oleh PT B, untuk offshore installation dimenangkan oleh PT C. Tapi ada juga untuk EPCI ini dimenangkan oleh satu perusahaan.

                E stands for Engineering,
                Engineering is body/company who have designed a project. Here will be discussed and decided about a system made, material consumed, manpower required included skill and competency, method agreed, machine used and how to manage activities and communication flow among discipline, management, contractor, client, owner, third parties inspection and classification

                P is Procurement,
                Normally procurement is how to procure after dealing with supplier and vendor material and schedule delivery and receiving and where are put ; warehouse or need certain condition reservation

                C is Construction,
                Construction is done in site, usually in a yard. Normally yard is located in seashore in order easy to bring product CPP or modules to offshore installation location. First maybe preparation of civil and foundation activities, than structural installation, piping installation, electrical installation and instrument installation, and lastly pre commissioning.

                I is Installation,
                After fabrication finished, next stage is installation. the product will be pulled to edge of sea and put on the barge and do sea fastening and ready to sail away to installation place. During this time shall be prepared all items for offshore installation, lifting equipment capacity, competent crews, scenario of installation etc

                Sekarang kita jump to topic about Electrical & instrument drawing. Actually each client or owner or company have their specification. They have their own terminology like few companies use term “grounding” ,others use term “earthing”. All terminologies actually are agreement in specification /datasheet/manufacturing sheet. All depend how they define and name in their document

                ELECTRICAL DESIGN DRAWING
                Electrical/PAGA/Navigational Aid index, legend, symbol & notes
                Electrical/PAGA/Navigational Aid single line diagram or one line diagram
                lectrical/PAGA/Navigational Aid block diagram
                Electrical/PAGA/Navigational Aid schematic/logic/loop/wiring/interconnection diagram
                Electrical/PAGA/Navigational Aid layout
                Electrical/PAGA/Navigational Aid installation Details
                Electrical/PAGA/Navigational Aid cable/panel Schedule
                Electrical main tray/ladder support detail
                Hazardous area classification
                Electrical design miscellaneous

                ELECTRICAL SHOP AND INSTALLATION (Field Run) DRAWING
                Electrical power routing layout
                Electrical Power tray support layout
                Electrical Power tray support detail
                Electrical Power mounting support layout
                Electrical Power mounting support detail
                Electrical Equipment support layout
                Electrical Equipment support detail
                Lighting cable routing
                Lighting tray support layout
                Lighting tray support detail
                Lighting mounting support layout
                Lighting mounting support detail
                Navigation aid mounting support layout
                Navigation aid mounting support Detail
                PAGA cable tray support layout
                PAGA cable tray support detail
                PAGA mounting support layout
                PAGA mouting support detail
                Electrical/PAGA cable penetration layout
                Electrical/PAGA cable penetration detail
                Electrical Shop Miscellaneous

                INSTRUMENT DESIGN DRAWING
                Instrument/ Fire & Gas/Telecommunication index, legend, symbol & notes
                Instrument process cause & effect diagram
                Instrument safety cause & effect diagram
                Instrument shutdown hierarchy diagram
                Instrument blok diagram
                Instrument interconnection/loop /termination/wiring/interface/schematic/logic diagram
                Instrument layout
                Instrument installation/support/mounting detail
                Instrument hook up
                Instrument cable/tubing/panel schedule
                Instrument level sketches
                Instrument main tray/ladder support detail
                Instrument miscellaneous

                Fire and Gas cause & effect diagram
                Fire and Gas single line/interconnection/loop diagram /termination/
                Fire and Gas wiring/interface/schematic/logic diagram
                Fire and Gas block diagram
                Fire and Gas layout
                Fire and Gas installation/mounting detail
                Fire and Gas miscellaneous
                Safety Escape route/sign layout

                Telecom single line diagram
                Telecom /interconnection/loop diagram /termination/wiring/logic diagram
                Telecom cable routing layout
                Telecom block diagram
                Telecom layout
                Telecom installation/mounting detail
                Telecom miscellaneous

                INSTRUMENT SHOP/INSTALLATION DRAWING
                Instrument mounting support layout
                Instrument installation detail
                Instrument tubing routing
                Instrument tubing tray support Layout
                Instrument tubing tray support detail
                Instrument cable tray support Layout
                Instrument cable tray support detail
                Fusible plug mounting layout
                Fusible plug detail
                Fusible plug tray support Layout
                Fusible plug tray support detail
                Fire & Gas mounting support layout
                Fire & Gas mounting support detail
                Fire & Gas cable tray support layout
                Fire & Gas cable tray support detail
                Telecom mounting support layout
                Telecom mounting support detail
                Telecom cable tray support layout
                Telecom cable tray support detail
                Instrument Tubing/cable Penetration layout
                Instrument Tubing/cable Penetration Detail
                Instrument Junction Box Support layout
                Instrument Junction Box Support Detail

                Few drawing samples for Electrical Discipline :
                1. Legend. Legend tells all symbols which are used in drawing in order whoever read drawing can understand everything on drawing
                There are several national and international standards for graphical symbols in circuit diagrams, in particular:
                · IEC 60617 (also known as British Standard BS 3939)
                · ANSI standard Y32 (also known as IEEE Std 315)












                2. Single line diagram. Ada juga memakai istilah one line diagram. Ini biasa nya men deskripsi kan tentang aliran daya listrik, start from generator, bus duct, switchgear, transformer, ke distribution board, than supply untuk
                - motor /pump/ fan/ compressor
                - space heater
                - lighting
                - fire and gas panel
                - Public address and general alarm panel
                - Telecommunication panel
                - Instrument supply panel etc









                3. Block diagram. Di dalam block diagram biasa nya menggambarkan interrelationship among system and existing equipment in global view, usually for electrical about cabling relationship. Below are lighting block diagram sample









                4. Wiring diagram/Interconnection diagram/loop diagram/schematic diagram. so far I have found They are almost same. All are about wiring or cabling detail for real connection. All connection should be labeled by tag no or cable marker for tracking and identification. Below are samples of Junction box







                and turbine-generator wiring connection.









                5. Plan or layout drawing. Plan show location of equipment. Plan usually base on system. E.g. lighting plan, fire and gas plan, public address and general alarm plan, telecommunication plan, navigational aid plan. Below is sample of fire and gas plan









                6. Detail installation drawing. These are detail installation for each equipments or detector or sensor which are given in plan drawing included with each bill of material for each installation. So each plan drawing will have all kinds of detail installation for all equipments /detectors /sensor which are put in plan drawing. Below is sample of strobe light installation detail










                Few drawing samples Untuk Instrument Discipline
                1. Instrument hook up. Hook up is similar with installation detail. See below picture










                2. Instrument Tray support detail. This tells about support of main tray or ladder












                3. Instrument layout. This give information about location of instrument in the field









                5. Instrument Fusible plug plan & detail