- Pastikan equipment certificate meet area classification requirement
- Remove temporary weather proofing, transport packing, and silica gel drying agent from switchgear, Cek cleanliness di dalam switchgear, specially for insulator
- Compare switchgear equipment meets equipment schedule, specially rating and any circuit changes
- Pastikan equipment meets spec, including weather, dust and vermin proofing
Switchgear post-installation inspection
- Check switchboard assy for alignment, level, tighteness foundation bolts and fixing in general
- Pastikan all panel doors and gland plate are bonded to switchboard structure
- Pastikan all equipment installed in switch board are in good conditions
- Inspect busbar joint
- Pastikan all insulators are clean, free from damage and not subjected to undue mechanical stress
- Cek all items corresponded to material list
- Cek all damages items
- Clearence phase to phase and phase to earth are acordance with spec
- Section clearances are satisfactory
- Earthing connection connected to all necessary points and clear of other metal
- Earthing connection tight, greased and thinned as required. Inspect the switchboard earth bar and earth cable for electrical and mechanical continuity
- Confirm all earth runs connected to main grid
- Labels correct/fitted
- Manufacturers name plate/marker correct/fitted
- Serial numbers match manufacturers test certificates
- Primary connection assembly /jointing compound, no undue stress/tension on equipment, fitting bolt correctly tensioned
- No dissimilar metals employed on primary connections
- No rust on equipment
- Site surfacing is correct and satisfactory
- All fixing bolts are tight
- No leaking impregnation fluid or swelling of containers
- Ensure all manufacturer's document and test certificate have been received
- Operation of locking facilities
- Cable entry arrangments
- Ensure all equipments meet specification weather, dust and vermin proofing after installation
- Examine fuses for rupturing or signs of deterioration
Switchborad testing
- After all busbar joints are completed but prior to securely fitting busbar covers, measure insulation resistance of the busbars and control wiring.
- Where there are any busbar joints, ductor test must be carried out prior to fitting covers. Simillar joints shall have a contact resistance within 10% of each other. The joints shall have a resistance equal or lower than an equivalent section of busbar
- Test switch board earth system for electrical dan mechanical continuity. Measure earth path resistance at the earth bar to the general earth system and earth bar joints
- Ensure that all protection relay have been tested accrdance with requirement of appropriate test certificate and vendor instruction
- Measure insulation testing of busbar and control wiring. Test should be carrued out prior to pressure test and before energising switchboard. Minimum acceptabe test result as below. A Power frequency voltage test (pressure test) on both main and outgoing cicuits sall be carried out phases and phases to earth.
Following conection shall be adhered for the tests
- All secondary sides of current transformers shall be short circuit
- All secodary sides of voltage transformer shall be open circuit
upon completion all tests, reconnect all cables and ensure that shorting links and fuses are replace